In Flanders, under the General Water Sales Regulation (Algemeen Waterverkoopreglement), the house connection (huisaansluiting) is the drain pipe running from the main sewer up to the rooilijn, the line between private land and the public domain. The private drainage (privéwaterafvoer) is the set of pipes, channels and appliances upstream of the rooilijn.
Source:codex.vlaanderen.be
In Flanders, only the sewer operator may install, modify, maintain and repair the house connection (huisaansluiting). The house connection is the property of the sewer operator.
Source:codex.vlaanderen.be
In Flanders, the sewer operator bears the cost of work on the house connection. It may ask the customer for a contribution when the customer requests the work or when the work is needed because of damage or a fault the customer caused.
Source:codex.vlaanderen.be
In Flanders, the customer or owner is responsible for installing, modifying, repairing and maintaining the private drainage and for keeping it in working order, and bears all related costs.
Source:codex.vlaanderen.be
In Flanders, where Farys runs the sewers, Farys states that owners are responsible for draining rain and waste water on their private land and that the sewer operator takes over from the rooilijn, the line between private land and the public domain. If the inspection chamber (toezichtputje) is empty, the blockage is in the private part and the owner has the unblocking or repair carried out.
Source:farys.be
In Flanders, in municipalities where Fluvius is the sewer operator, Fluvius’s technical regulation places the maintenance of the private drainage and of the part of the house connection up to and including the connection inspection chamber (huisaansluitputje) on the customer. In case of a blockage, the customer must first check that it lies beyond that chamber before calling the operator.
Source:fluvius.be
In Flanders, the private drainage must be inspected for a new build or rebuild, for a new additional house connection or the installation of an individual treatment system, and when a separate sewer system is laid in the public domain, unless there is an inspection for a new build or rebuild no more than five years old.
Source:codex.vlaanderen.be
In Flanders, customers request the private drainage inspection themselves and pay for it. AquaFlanders and Vlario train and accredit the inspectors.
Source:vmm.vlaanderen.be
In Flanders, complete separation of wastewater and rainwater from roofs and ground surfaces is mandatory as soon as a separate sewer system is laid or relaid, unless the implementation plan provides otherwise.
Source:codex.vlaanderen.be
In Flanders, where household wastewater goes is not a free choice: the municipal zoning plan sets, address by address, how it must be handled.
Source:vmm.vlaanderen.be
In Flanders, buildings in the individually optimised rural area must eventually have their own wastewater treatment system (IBA). For new builds it must be installed immediately; for existing buildings, the municipality or sewer operator makes contact when the IBA has to be installed.
Source:vmm.vlaanderen.be
In Flanders, in the individually optimised rural area, a septic tank receiving both black and grey wastewater, with a capacity of at least 3,000 litres, is mandatory pending an IBA.
Source:vmm.vlaanderen.be
In Flanders, emptied septic tank material may not be discharged into public sewers or collectors; it must be taken to a public wastewater treatment plant.
Source:codex.vlaanderen.be